6. Operation
6.1 Start Up Procedure
!
WARNING
Before turning on the inverter, ensure that the front panels are closed properly.
!
AVERTISSEMENT
Assurez-vous de la bonne fermeture des panneaux antérieurs avant de mettre
l’onduleur en route.
To start the inverter, complete the following steps in order:
1. Prior to engaging the disconnect switches, check the polarity of the DC positive and
negative connectors to ensure they are wired correctly and conrm the PV panel
open circuit voltage is at or below 600 VDC.
2. Close all upper and lower cabinet doors.
3. Turn on the external AC connection to the inverter.
4. Turn on the external DC disconnect to provide DC power to the inverter.
5. Turn the ON/OFF switch to the OFF position.
The ON/OFF switch is located next to the display screen.
6. Turn the inverter’s AC disconnect to the power ON position. Refer to Figure 6-1.
The display on the upper front panel should now be active. The display is shown
in Figure 6-3.
7. Turn the inverter’s DC disconnect to the power ON position. Refer to Figure 6-1.
8. Turn the ON/OFF switch to the ON position.
After ve minutes, the inverter starts to produce power into the AC grid if all necessary
operating conditions are met.